DAS Room – Distributed Antenna System Equipment

All Distributed Antenna Systems (DAS) require a DAS room for operator equipment and depending on the DAS topology deployed it could require additional locations of various sizes and configurations. We’ll detail some of the considerations of the ‘Main DAS equipment room’ which is typically required regardless of topology, whether active or passive.

This article has been updated for the new 2022 MCF. Please find our full article on the MCF update here.

Main DAS Room Location

One of the most important and cost impacting considerations is the placement of the DAS room within the overall building. DAS system topology choice is at the mercy of the coaxial cable distance of antennas from the Base Station equipment. As such a DAS room which is further away from the main comms riser may often be the deciding factor between a passive and active system, or the requirement for secondary equipment locations. Both consequences provide additional deployment and operator connection costs. Consequently, the placement of the DAS room can greatly impact the topology of the overall system. Typically, the DAS room is within the basement of a building but locating it on B1 centrally near the riser will produce better outcomes than B5 in a far corner from the communications riser.

DAS Room, DAS Room – Distributed Antenna System Equipment
DAS Room adjacent to Comms Riser
DAS Room, DAS Room – Distributed Antenna System Equipment
DAS room located far from Comms Riser

On a similar note, the layout of Communications risers and any transitions (doglegs) within the riser can impact the cable length and impact the topology choice for the system. Straight up and down risers allow for shorter cable paths, simpler installation and can minimise the need for active equipment and keep costs down.

Space Requirements for the Main DAS Room

The space requirements for a DAS room are largely influenced by the size of the building and, consequently the size of the DAS system. The requirements for a 20 story skyscraper would differ to that of a large multi-tower precinct. The space required largely relates back to the number of ‘sectors’ the DAS will require and thus influences the space required by the operator for their subsequent connection. MCF2018 provides for a minimum for 6 racks (MCF2022) per operator of 600x600mm dimensions as such to allow for Vodafone, Telstra and Optus would require 18 racks in total within the DAS room.

Typically, WCS would recommend that the minimum DAS room is appropriate for a 3-4 sector site which is most typical of a ~30 story office buildings. More unique sites or precincts require additional planning and consultation with the operators.

DAS Room, DAS Room – Distributed Antenna System Equipment
DAS Room planned for all operators

The DAS room can ultimately take a variety of physical shapes but needs to support a rack layout for not only the space requirements but also to allow for the doors of racks to open, movement space between the racks and work areas. A lot of which is dictated by the BCA and similar codes.

Most buildings expect to use their DAS for some time, consequently allowing for space within the DAS room to grow and expand is always a wise choice to facilitate future upgrades for additional operator equipment such as 5G.

A DAS with multiple equipment locations or an Active DAS will require fibre to link the various locations, and consequently require a dedicated rack (or more for larger sites) to hold the Fibre termination FOBOTs and the Active DAS Headend. Consequently, a 18-rack site may be closer to 20 in reality to support the common infrastructure elements. In fact the new MCF requires 2 racks be allowed for common equipment

Space within secondary DAS Rooms

There can be valid reasoning for deploying multiple DAS rooms throughout a building, for example, one at the top and one of the bottom to mitigate the loss of the coaxial cable. Historically this was known as a Remote Radio Unit (RRU) topology. The MCF2018 provides some guidance on this, recommending one rack per operator per location. But this is written with the conventional topology of a single sector being at each RRU location, and we often see attempts to wiggle around this and provide short sigted solutions. MCF2022 updated this to 3 racks per location per operator, which is more appropriate, along with power and cooling considerations.

Infrastructure Requirements for a DAS Room

Cable Tray

Cabling to the DAS room can often be significant and include a mixture of fibre and coaxial. Although not mandated by the MCF2018 clearly it is best practice to allow for a variety of cable tray to link the DAS room to the main communications riser. Tray around the room to facilitate the various interconnects between the operators and common DAS infrastructure can also lead to a well maintained and easy to troubleshoot layout. There should also be a tray or connection to a tray that ultimately provides a route to the building lead in point for operator transmission, this could be via the MDF room.

Communications Risers

Realistically somewhere in a Distributed Antenna System will be the use of Coaxial Cable in a vertical orientation traversing up a riser. We understand it can be tempting to have risers move 6 different times up the building, but the reality is Coaxial cable is distanced, limited and rigid with challenging bend radiuses. A riser should be straight up, and down a building, else one risks the need for several Active DAS remotes to be required at significant cost and complexity. Simple is best!

Fibre Connectivity

For DAS systems with multiple equipment rooms, it is common to link the various DAS rooms with single-mode fibre connectivity. The number of cores is variable depending on the configuration of the site.

Cooling

2x6kW cooling capacity be provided within the DAS room to allow for redundancy, this is often split systems in existing buildings, however, development sites may consider alternative ducted solutions to provide similar cooling capacity.

Electrical Considerations

Within the DAS room, electrical supply is required to provide for the three mobile operators equipment. Typically, this is in the form of a dedicated DAS Distributed Board within the DAS room with a 100A 3 Phase inbound supply. Any electrical supply required for the rooms cooling solution should be allowed in additional or fed independently elsewhere if ducted.

The individual operators will then install their respective configurations downstream from this main DAS board, typically in the form of 3 Phase 32A outlets.

Having the ability to switch over the DAS board to a generator during power outages (typically scheduled) provides for continuous connectivity onsite and may be desirable on a site by site level.

Wireless Coverage Solutions have experience deploying Distributed Antenna Systems for properties of all shapes and sizes and intimately understand the requirements for planning an appropriate DAS room and the implications to topology and cost. Don’t hesitate to contact us to discuss your next project.